#2671
@001 Enter the name of the OWNER:
@002 Enter the name of the CONTRACTOR:
@100 Enter the description of the work to be performed:
@101 Enter estimated completion schedule:
!102 Enter the contract price:
#2672 Do you want to specify materials to be used?
#if#2672
@300 Specify areas specified:
@301 Enter specifications:
#endif
#2673 Will the contractor pay for permits?
#2674 Will contract be required to provide proof of insurance?
#if#2674
!103 Enter insurance limits required (in numerals):
#endif
#2675/#2676/#2677 Draws will be based on:
1/3 Rough in;1/3 inspection;1/6;1/6
Weekly draw on per centage of completion
Joint checks on materials; 1/3;1/3- 1/6,1/6 on labor
#2678 Is contractor required to remove trash?
#2679
#end control section
#2671
/* Para. 2671: Contract for remodeling, large */
CONTRACTING AGREEMENT
@001, referred to as OWNER, and @002, referred to as CONTRACTOR,
agree as follows:
CONTRACTOR shall perform the following services for OWNER:
@100
on the following estimated schedule:
@101
for the following price: $ @102 (!102 dollars)
Contractor shall be responsible for the following in addition to
the workman like performance of the work stated above:
#2672
/* Para 2672: Spec of materials */
The materials used for the following areas:
@300
shall meet the following respective specifications, or be
equivalent to the following manufacturer's product lines
described:
@301
#2673
/* Para 2673: Permits */
Provision of all permits required for the services to be performed
above.
#2674
/* Para 2674: Insurance*/
Provision of worker's compensation insurance, general liability
insurance in a minimum amount of $ @103 (!103 dollars).
#2675
/* Para. 2675: Draw sked */
The stipulated contract price shall be paid as follows:
1/3 on rough in; 1/3 on first inspection and 1/6 on final
inspection and 1/6 on final inspection and completion of all
appearance/punch list in items.
#2676
/* Para. 2676: Weekly draw based on per centage of completion*/
The stipulated contract price shall be paid as follows:
A weekly draw based upon per centage of completion, less a
retainage of 10% per cent, which shall be paid on final
inspection and completion of appearance/punch list items.
#2677
/* Para. 2677: Bills for materials */
The stipulated contract price shall be paid as follows:
When bona fide bills for materials are presented the same shall
be paid directly by the OWNER within the terms provided. Labor
shall be paid as follows:
1/3 on rough in; 1/3 on inspection; 1/6 on completion; 1/6 on
final inspection and completion of appearance/punch list items.
#2678
/* Para. 2678: Removal of trash */
The CONTRACTOR shall daily remove all trash and debris from the
premises.
#2679
/* Para. 2679--- closer */
This is the entire agreement between the parties and this
agreement may only be altered in writing.
Dated: _________________________
____________________________________________________
@001
____________________________________________________
@002